Risk Related Fields

Most likely time of the risk occurrence

Name of parameters (shown on the tool tip)

Most likely time of the risk occurrence

Type of the field

Edit Box With Spin Control

Short name (shown in the header)

Most Likely

Description

Risk most likely will occur at this time. Time is defined as a percent of total task duration. For example, task duration is 5 days. Most likely risk occurrence of 50% means that most likely, the risk will occur at the middle of third day.

Related Fields

Start Time

Finish Time 

 