User's Guide to
RiskyProject Professional
Risk Related Fields
Finish time of the risk occurrence
Name of parameters (shown on the tool tip)
Type of the field
Edit Box With Spin Control
Short name (shown in the header)
Finish
Description
Risk cannot occur after this time. Time is defined as a percent of total task duration. For example, task duration is 5 days. Finish time of risk occurrence 80% means that risk will occur before the end of fourth day.
Related Fields
Distribution
Distribution Chart
Copyright © Intaver Institute Inc., 2002-2006. All Rights Reserved