The type of link between different tasks. There are four types of task dependencies:
-
Finish-To-Start: Task 2 (successor) cannot start until task 1 (predecessor) finishes
-
Start-To-Start: Task 2 (successor) cannot start until task 1 (predecessor) starts
-
Finish-To-Finish: Task 2 (successor) cannot finish until task 1 (predecessor) finishes
-
Start-To-Finish: Task 2 (successor) cannot finish until task 1 (predecessor)
starts
Task
dependencies can be defined in Task Information dialog box (predecessor tab). They also can be defined toolbar button within standard toolbar. |