User's Guide to  

RiskyProject Professional

Back to RiskyProject Professional
Project Risk Management and Decision Analysis 

Project Risk Management Glossary

 

Duration

The total span of working time required completing task or whole project. Task duration can be input in months, weeks, days, hours, and minutes, as it is specified in Options dialog box (Duration tab). Internally duration is calculated in hours. Duration is calculated using current calendar.

See Also:

Start Time

Finish Time


 